Pictures and Maps of Current Construction and Closures
BROS-CO97(82)
BROS-CO97(84) Original Structure
BROS-CO97(89) July 7, 2008
BROS-CO97(89) Original Structure
BRS-CO97(80)
L-B05(5) Original Structure
L-C06(1)
| Current Road Construction and Road
Closure Report |
|
Last
Updated -
7/22/2008 11:03:16 AM
Project BRS-CO97(80) Bridge completed and road opened to traffic July 1, 2008.
Project L-C06(1) Culvert completed and road opened to traffic. Paving of approaches to be completed this summer.
Project BROS-CO97(82) Culverts completed and road opened to traffic.
Project BROS-CO97(84) was let February 19, 2008 and a contract awarded to Midwest Contracting LLC, Marshall, Minnesota. The project is on County Road D-22 AKA 160TH Street over a tributary of Bacon Creek in Section 2 of Rock Township. The existing 26’x24’ single span steel beam bridge with concrete deck will be replaced by a 12’x10’58’ twin reinforced concrete box culvert. Construction should begin late July 2008 and is scheduled for completion in August 2008. County Road D-22 will be closed to through traffic at the project location. Access for residents will be maintained.
Project BROS-CO97(89) description coming soon...
Project L-B05(5) description coming soon...
Thank you, Woodbury County Engineers
back
|